BIM supports gas mains replacement work on Albert Court

317
Albert Court, BIM, gas mains replacement,

Morrison Utility Services and Skanska UK joint venture, tRIIO, has utilised BIM to complete major gas mains replacement work on Grade II listed building, Albert Court

tRIIO has completed major gas mains replacement work on Albert Court, a Grade II listed building situated adjacent to the Royal Albert Hall.

The project to replace the ageing gas mains was delivered on behalf of Cadent by tRIIO design and multi-occupancy building (MOB) teams.

Due to the complexity of the building, the mains replacement works had been put on hold for several years.

In order for works to begin, a full planning application was required, alongside approval from Historic England. A key priority was the conservation of Albert Court’s authentic exterior, including all original features such as its century-old stained glass.

3D drawings

The need to provide a detailed and accurate proposal was paramount.

With longhand drawings and elevation plans likely to prove problematic in navigating Albert Court’s long, narrow lightwells, the design team used Building Information Modelling (BIM) to create detailed 3D drawings to illustrate how the replacement gas network would look against the structure of the building.

The framework of Albert Court was 3D laser point scanned and imported into BIM as the base to design and deconflict the 1.2km of external pipework required.

During the preconstruction stage, the cloud-based virtual building was used to perform the ‘Scan to BIM’ (S2B) exercise and develop an intelligent building (BIM) model which represented the architectural surface, structure and services.

Following the preliminary design of gas mains, networks pipes, risers and approved entry point modelling, 4D scheduling was developed to reflect the project timeline. This scheduling was used along with 5D quantification to ensure accurate quantities of materials were delivered to the site’s limited onsite storage facilities.

BIM specialist Nathan Mohan, who oversaw the process, said: “The silo design and installation reduced redundant design attempts and unnecessary installation costs.

“Each development stage was instantly quantified to reduce logistical complications and help stick to budget.”

Collaboration

Collaborative working was a key element of the project’s success as the onsite tRIIO team adapted its programme of work to accommodate other contractors working on the development of new apartments in the building. The team ensured the network was set up to enable the building contractor to deliver work without any impact on the building’s supply and to support any future renovations in the building.

tRIIO Project Manager, Mark Williamson, added: “Such intricate planning was vital in receiving stakeholder buy-in and made working on this ornate building more straightforward than a standard building would normally be.

“The detail provided through the adoption of BIM technology played an instrumental role in supporting our stakeholder engagement plan and ensuring full understanding of the plans.

“I’m proud of the work the team has done on such a high profile property and look forward to unlocking the potential of BIM technology in the future.”

Editor's Picks

LEAVE A REPLY

Please enter your comment!
Please enter your name here