John Newcomb and Peter Caplehorn, co-chairs of the Construction Leadership Council’s Product Availability working group, have released a statement regarding future product availability in the industry

While the market is no longer experiencing the high levels of demand seen earlier this year, UK manufacturers remain at full production capacity as demand continues to outstrip supply for certain products, particularly those being imported.

However, the overall verdict remains more positive, with improved availability of most products across most regions.

Ongoing challenges still remain regarding brick supply, blocks and roofing products, where timber battens have overtaken concrete roof tiles as the most difficult to obtain, and certain electro-technical products.

Residential repair, maintenance, and improvement activity remain robust, with most SME builders reporting full order books well into 2022.

The sector has recently seen a small but noticeable slowing, as a consequence of delayed projects and increased costs and lead times, and seasonality.

This softening has helped improve some stocks, such as cement, held by manufacturers and merchants.

Activity across the infrastructure, commercial and new housebuilding sectors continues unchanged, and will likely remain so into the first half of 2022.

Reports from larger housebuilders and contractors suggest that while a variety of product shortages persist, the situation for most remains manageable.

Brick demand continues to rise

Last month, reports have shown that brick supply presents a longer-term issue, and imported products are helping to meet a shortfall in current UK capacity until new lines come on stream in 2023 and 2024.

The Brick Development Association suggests that with demand expected to remain high, lead times will be an issue for the coming year.

For builders to ensure that they get the bricks they need, particularly if they are seeking non-stock bricks, they will have to work more closely with the brickmakers to ensure availability and to mitigate delays in delivery.

While this may require flexibility around choice and specification, quantities should be sufficient to meet demand.

Consistently high demand over the past 18 months has also made it difficult for block manufacturers to build the level of stocks required to maintain regular supply throughout the year.

Manufacturers are seeking to build stocks over the coming winter months while building sites are typically less active.

Nonetheless, demand from new housebuilding is expected to put the supply of blocks under pressure in early 2022.

Timber stocks have shown slight improvement

Stocks of timber have seen some improvement, though prices remain volatile.

Market reports reveal significant delays at ports both here and abroad, having a knock-on effect upstream to the Scandinavian mills where production has been forced to slow.

This suggests that supplies may remain uneven into early 2022.

In the electrotechnical sector, products with electronic components and those made from steel, such as cable trays remain in short supply, while twin and earth cable has become more problematic.

Product pricing continues to be a challenge, particularly for medium-sized contractors working on tight fixed-price contracts.

Reported constraints relating to a shortage of HGV drivers have lessened for the time being, though the pre-Christmas period may cause further pressure.

Uncertainty for future supply availability

Uncertainty is now cited as a broad area of concern, including uncertainty around inflation and the pricing of products, particularly in relation to steel, cement, bricks, blocks, glass and ceramic tiles, which are all impacted by rising energy costs.

Potential spikes in Covid-19 cases over the winter period are also having an adverse effect on product availability.

The impact of full border controls that come into force at the end of this year is a further unknown, as is the implementation of the new UK CA Mark and UK Registration, Evaluation, Authorisation & Restriction of Chemicals (REACH) regulations.

In response to this, the CLC is working with the Department for Business, Energy & Industrial Strategy to build on the industry-wide perspective of the PAG and the data it can access, using horizon scanning to identify medium-term problems affecting materials and product availability that can be mitigated by an agreed, planned response.