Liverpool £25m Greener Grid Park enters final stages of construction

478
Greener Grid Park

Liverpool’s Greener Grid Park, a £25m zero carbon scheme to increase green energy use, has entered the final stages of construction

The project, being carried out by Statkraft, will see the Greener Grid Park built off Lister Drive in Tuebrook.

The scheme aims to help to remove fossil fuels from the UK’s energy supply and maximise the amount of renewable energy that can be distributed through the grid.

‘A need for additional stability services to the Liverpool grid’

Planning permission was initially granted by Liverpool City Council in 2020 after National Grid ESO identified a need for additional stability services to the Liverpool grid.

The site will mimic the spinning turbines of a traditional power station, providing the high inertia that grid operators rely on to maintain grid stability.

As power from renewable sources like wind and solar is fed into the structure, a 67 megavolt amps reactive synchronous condenser, coupled with a 50-tonne flywheel, provide the inertia required to ensure the network frequency and voltage are held stable.

Contractors NRS Group have now finalised all major construction work at the site.

“The Lister Drive Greener Grid Park will not only create more opportunities for the city to use green energy but will also contribute to the local economy through jobs and suppliers.”

Following a period of testing, the site will be handed over to Statkraft, with operations and long-term maintenance services provided by ABB.